Cherry Valley uses two offices for one backyard project. The village issues the zoning permit, and Winnebago County's Building Division issues the building permit, and the village's own code says the county will not release a building permit until the zoning permit is in hand. That split is the first thing to understand about a fence, a shed, a deck or a pool here.

If you are looking at homes for sale in Cherry Valley, the permit history of the yard is worth as much attention as the age of the roof. Gambino Realtors has worked in the Rockford area since 1923, and this guide sticks to what the village's published code, its forms and the county's pages actually say. It covers who issues what, the numbers the code sets for fences, sheds, decks and pools, and how a buyer can find out whether the work in the yard was ever approved.

Two Offices, One Project: Village Zoning And County Building

The Village of Cherry Valley's Forms and Permits page lists what needs a permit in plain terms. A new residential home or commercial building does. So do decks, fences, garages, accessory buildings, cement slabs, in-ground pools, room additions and signs. The page adds that if your project goes beyond what the village ordinance allows, you need a variance. Questions go to Village Hall at 815 332-3441, and applications can be faxed or mailed to 806 E. State Street.

The form itself is a single sheet called the Village Zoning Permit and Building Permit Application. It asks for the owner, the contractor, the street address and the township, and it has check boxes for new construction, addition, fence, deck, storage building and other. It also asks for a drawing. The drawing has to show the lot dimensions, the front, side and rear yard setbacks, the size and square footage of existing and proposed buildings, and the distance from the new structure to each property line.

Read the notices printed on that form, because they are the village's own warnings. A zoning permit is valid for up to one year from the date it is issued. All construction must match the drawing you attached. It is the applicant's sole responsibility to know where the property lines are. A fence also cannot block or close in shared utility boxes such as the electric, cable or phone boxes.

The footer of the form then points you to the second office. A building permit for the project is obtained from the Winnebago County Building Department at 404 Elm Street in Rockford, phone 815-319-4350. The county's Building Division page confirms that it services the Village of Cherry Valley along with Durand, New Milford, Rockton, Roscoe, South Beloit and unincorporated Winnebago County. It also publishes reference sheets that matter to this topic, including deck specifications, joist layout, stairs and railings, and electrical requirements for swimming pools, spas and hot tubs.

How do the two permits relate? The village code answers that directly. Section 82-114 says the county building officer shall not issue building permits for structures unless they conform to an approved zoning permit. Section 82-113 says the county building officer shall not issue a certificate of occupancy until all conditions of the zoning permit are met. And section 22-1 says the village has adopted the building codes that Winnebago County has approved, along with chapter 18 of the county code. So the village decides where a structure may go and how big it may be. The county decides whether it is built to code.

That arrangement has a practical consequence for buyers. Each office keeps its own record, so a clean file at one office does not prove a clean file at the other. A structure with no application at either office has no file at all, and the only way to learn that is to ask both.

The village keeps its own records. Section 82-51 says the zoning officer issues all zoning certificates and certificates of zoning compliance and keeps permanent records of them. That is the document trail you want to ask about. We come back to how to ask for it below.

One note on cost. The code says the fee for a zoning permit is whatever the village's zoning, land use and development permit fee schedule sets at the time, and that decks, fences, porches, patios, storage sheds and aboveground pools pay the application fee in that schedule. The code also says no application fee applies when you are enclosing an existing porch or an existing concrete slab. Because the schedule can change by resolution, ask Village Hall for the current figure instead of trusting an old number.

What The Village Code Sets For Fences, Sheds, Decks And Pools

The numbers below come from the Code of Ordinances as the village publishes it, codified through an ordinance adopted in November 2024. Codes get amended, so treat this as the rule set to ask about, not the last word. The zoning officer at Village Hall confirms what applies to a specific lot.

Fences

Section 82-7 holds the fence rules. On an interior lot, a fence, wall or hedge may be up to four feet high in a front yard. In side and rear yards the limit is six feet. Corner lots have a vision-clearance triangle at the intersection, and nothing there may be allowed to grow or stand in a way that blocks the view above the plane of the street grades. Anything that conflicts with a traffic signal or sign can be removed.

The code is specific about how a fence is built and what it is made of. A sight-tight fence has to be installed with the finished side facing outward, toward the neighbors and the street, and no posts or supports may be visible from outside the lot unless the zoning officer approves it for that type of fence. Before a fence permit is issued, the applicant gives the village an engineered drawing or a product specification sheet that shows the dimensions and the finished look. Permitted materials are naturally resistant or treated wood, brick or masonry, wrought iron, vinyl or composition plastic, and galvanized or coated chain link. Galvanized panels are not allowed, and fluorescent paint is prohibited.

There is a second set of rules for residential lots that touch a public road, and it is stricter than the first. Fencing next to the roadway may not exceed 48 inches. Fencing is not allowed from the rear of the house forward to the street along the side and front yards, unless the zoning officer authorizes it because of unusual conditions on the lot. Every fence has to sit at least three feet in from the inside edge of the sidewalk, which leaves a strip of green space visible from the road. For a corner house, that can change a plan a great deal. A six-foot privacy fence that works on an interior lot may not be available on the street side of a corner lot.

Some fencing needs no permit at all. Snow fencing is allowed from November 1 through March 31, and garden fencing such as chicken wire or field fencing is allowed from April 1 through October 31. Construction fencing is allowed only while a building permit is active. Outside those windows, a fence is a permanent fence and goes through the process.

Sheds, Garages And Other Accessory Structures

Section 82-10 covers accessory structures in the R1, R2 and R3 residential districts. The code's list of covered structures is wider than most owners expect. It names gazebos, pergolas, storage and garden sheds, greenhouses, swimming pools, hot tubs, cement or asphalt pads, pigeon lofts, playhouses, garages and fire pits. None of them may ever be used for living quarters.

The limits are numbers you can check against a lot with a tape measure:

  • No more than two accessory structures per lot. A garage and its driveway count as one structure.
  • Total accessory space of 600 square feet if the house has an attached garage, and 800 square feet if it does not.
  • A maximum height of 15 feet.
  • Siding and roofing that is not reflective, in a neutral color with a complementing trim color. Prefab garden or tool sheds of 120 square feet or less are exempt from the color rule.
  • A location at least 20 feet beyond the rear of the house.
  • Side and rear setbacks of six feet, with no part of the structure, including the roof, overhang and gutters, reaching into them. If the approved plat shows a different setback, the plat controls. Nothing may sit on an easement.
  • No plumbing, except in swimming pools and hot tubs. Electricity requires a permit from the county building department.

The setback counts the roof, the overhang and the gutters, not just the walls, so a shed that sits seven feet from the line can still fail if its eaves reach past the six-foot mark. And the easement rule reads "at no time." The application form puts the burden on the applicant to know where the property lines are, and the code asks for a drawing that shows utility easements.

The approval path is longer than a one-page form suggests. After the application is filed, the zoning officer visits the lot and photographs the house and the proposed spot. If the officer believes a variance is needed, the package goes to the planning and zoning commission. Otherwise it goes straight to the village board. The commission reviews and votes on a recommendation, and the board votes to approve or deny. An unfavorable recommendation from the commission takes a super majority of the board to overrule.

The penalty for skipping this is spelled out in the same section. A structure built or moved on without approval can be required to be dismantled or removed, at the homeowner's expense. Fines run fifty dollars a day, each day counted as a separate offense, starting the day construction began or the portable structure arrived. Because the fines count by the day, the code reads an unapproved structure as a continuing violation.

Portable storage containers, the kind delivered for a move or a renovation, have their own chapter. Chapter 32 requires a permit before one is placed on a residential lot. You apply in writing at least 14 days before delivery, there is no fee, and the permit covers 30 days, which must fall within a six-month window. Only one container is allowed. It goes on a paved surface unless new home construction is underway, never on a right-of-way or easement, and it may be at most 20 feet long, 8 feet high and 10 feet wide, set back at least 5 feet from a right-of-way or easement.

Decks, Patios And Concrete

Decks sit on the village's list of items that need a permit, and the application form has a box for them. The county Building Division publishes deck specification sheets covering footings, joist layout, and stairs and railings, and those are the standards an inspector measures against. The zoning side asks where the deck goes. Section 82-7 treats open terraces not more than four feet above the adjoining ground, and steps four feet or less above grade, as allowed in a required yard. A raised deck is measured against the same setback and yard rules as any other structure, and the drawing on the application has to show it.

Concrete deserves its own sentence, because owners forget it. The code says no impervious surface may be built in any setback required by the zoning code, and the village lists cement slabs among the things that need a permit. A new patio or a widened driveway can break the rule as easily as a shed.

Pools

The pool rules appear in three places, and they agree. The village's definition, on its swimming pool safety sheet, is a structure intended for swimming or recreational bathing that is at least 24 inches deep. That includes above-ground, on-ground and in-ground pools, inflatable pools, hot tubs and spas. Section 22-105 of the code requires a barrier at least 48 inches high around any private pool, in-ground hot tub or spa holding more than 24 inches of water. The gates must be self-closing and self-latching. If the self-latching device is less than 54 inches above the bottom of the gate, the release mechanism has to be on the pool side of the gate.

The village's handout adds detail. A barrier cannot have openings of four inches or more. Lattice-type barriers may not have openings larger than 1 and 3/4 inches, and chain link mesh may not exceed 2 and 1/4 inches square. For an above-ground pool taller than 48 inches, the pool wall itself can serve as the barrier, as long as the ladder or steps can be locked, secured or removed. Section 82-7 adds that a pool enclosure is a wall, fence or hedge between four and six feet high.

The handout also explains why a pool permit exists. The permit lets the village verify that the pool is not in an easement, a floodway or a setback, that the barrier requirements are met for the kind of pool, and that it is not in the required rear or side yard. For the wiring, the county has a swimming pool electrical sheet.

Floodplain lots add one more layer. Chapter 30 says no development may start in a floodplain without a development permit from the village. If someone ignores that, the code says the village shall record a notice of violation on the title of the property, and that the owner is to be told the violation may cause coverage under a standard flood insurance policy to be suspended. Our guide to flood zones and flood insurance explains how the federal maps work. Ask the village whether a lot you are considering lies in a floodplain.

Why Permit History Matters, And How To Check It

The code puts the responsibility on whoever owns the lot when a problem is found. Section 82-10 says a structure built or moved on without approval can be required to be dismantled or removed at the homeowner's expense.

Picture the version of this that the code makes possible. A buyer likes a house with a detached shed. The inspection report says the shed is sound. The zoning officer's records hold no application for it, and it sits five feet from the side line. The code's six-foot side setback has no stated exception for a shed that someone else built without approval, and the code says such a structure can be required to be removed at the homeowner's expense. That is a hypothetical, not a record of any one property, and it shows why the question belongs before closing.

The state's seller disclosure form does not catch this. Item 23 on the Illinois Residential Real Property Disclosure report asks whether the seller has received notice of a violation of local, state or federal laws relating to the property that has not been corrected. That is a useful question, but it is not the same as asking whether past work was permitted. A seller can truthfully answer no, and the deck can still have no paperwork. Our guide to the Illinois seller disclosure report walks through what the form does and does not say.

A home inspection is not a permit review either. An inspector reports on condition, and a deck can be well built and still unapproved. What a home inspector looks at is covered in our guide to what the inspector checks. The permit question is separate, and you have to ask it separately.

Here is a short, practical way to check permit history on a Cherry Valley house:

  • Walk the lot and list everything added. Fences, sheds, decks, patios, pools, hot tubs, additions, finished basements and slabs all count.
  • Ask the seller, through the listing agent, for the permits, drawings and inspection sign-offs they have, and for the date each item was built.
  • Call Village Hall at 815 332-3441 and ask whether the zoning officer has a record for each item, since the code says the zoning officer keeps permanent records of zoning certificates.
  • Call the Winnebago County Building Department at 815-319-4350 and ask about building permits and inspection records at that address, particularly for electrical work, decks and pools.
  • Compare the lot to the numbers above. Measure the shed's distance from the side and rear lines, the fence height, and whether the fence sits three feet back from the sidewalk if the lot is on a road.
  • Put anything that fails the comparison in writing with your agent, before the inspection period ends, and decide whether to ask the seller to cure it, adjust the price or walk.

The village also has a way to fix a problem legitimately. A structure that does not meet the code can be brought into compliance through a variance. The zoning board of appeals recommends variations for things like a smaller yard than required, a taller structure, or a fence above or below the limit, and the village board decides. The code says cost alone is not enough of a reason. The applicant has to show a practical difficulty or hardship tied to the lot, such as its size or shape. The application asks for the adjoining owners' names, a scale drawing and a legal description. It also asks for a soils report from the Winnebago County Soil and Water Conservation District, and the form says the fee is doubled if the improvement is already built or under construction. Publication costs are added on top.

That doubled fee is a quiet argument for asking before you build, and for asking before you buy. Fixing an approval after the fact costs more, and the answer can still be no.

Bottom Line

In Cherry Valley, the village decides where a structure goes and the county decides whether it is built right, and a fence, shed, deck or pool needs both. The village's code gives you the numbers to test any yard against: four feet in front and six feet on the sides and rear for fences with tighter limits next to a road, six-foot setbacks and a 600 or 800 square foot cap for accessory space, a 48-inch barrier with a self-latching gate for pools.

If you are buying, treat permits the way you treat the roof. Ask the seller for the paper, call the village and the county for the rest, and put what does not match in writing while you still have room to negotiate. If you are selling, collect the permits and sign-offs before you list, because a clean file keeps a buyer's questions short. When you are ready to look at homes for sale in Cherry Valley, bring the address and the checklist above. For everything else Gambino Realtors has written about the area, the Illinois Real Estate Guide is the index.

That is a lot of numbers in one place.

Frequently Asked Questions

Do I need a permit for a fence in Cherry Valley?

Yes, for a permanent fence. The village lists fences among the projects that need a permit, and the code asks for an engineered drawing or a product specification sheet before a fence permit is issued. Snow fencing from November 1 through March 31 and garden fencing from April 1 through October 31 need none. Call Village Hall at 815 332-3441 to confirm what applies to your lot.

How tall can a fence be in Cherry Valley?

On an interior lot the code allows four feet in a front yard and six feet in side and rear yards. Residential lots that touch a public road have a stricter rule. Fencing next to the roadway is limited to 48 inches, it may not run forward of the rear of the house along the side and front yards without the zoning officer's approval, and it must sit at least three feet inside the sidewalk.

Do I need a permit for a shed in Cherry Valley?

Yes. The village lists storage sheds and accessory buildings among the items that need a permit, and section 82-10 sets the limits for residential districts. Each lot may have two accessory structures, up to 600 square feet of total space with an attached garage or 800 without, no taller than 15 feet, with six-foot side and rear setbacks. Prefab sheds of 120 square feet or less are exempt from the color and window rules.

Who issues the building permit for a deck or pool in Cherry Valley?

Two offices are involved. The village issues the zoning permit and checks location and size. The Winnebago County Building Department, at 404 Elm Street in Rockford, issues the building permit and inspects the construction. The village code says the county will not issue a building permit unless the project conforms to an approved zoning permit, so the village step comes first.

What happens if a house has a shed or deck with no permit?

For a shed or other accessory structure, section 82-10 says it can be required to be dismantled or removed at the owner's expense, with a fine of fifty dollars a day counted from the day construction began. A deck or pool with no county permit can raise questions at a sale or an insurance claim. The village can also bring a zoning violation under section 82-57, which carries a fine of one hundred to seven hundred fifty dollars per offense.

Does the Illinois seller disclosure report tell me about unpermitted work?

Not directly. Item 23 asks whether the seller has received notice of a violation of local, state or federal laws relating to the property that has not been corrected. It does not ask whether a deck, shed or pool was permitted, so a seller can answer no and the work can still be unapproved. Check the village and county records separately.

Can I get a variance if my fence or shed breaks a Cherry Valley rule?

You can apply. The zoning board of appeals recommends variations such as a smaller yard, a taller structure or a fence above the height limit, and the village board decides. Cost alone is not a sufficient reason. The application needs a scale drawing, a legal description, the adjoining owners and a soils report, and the fee is doubled if the work is already built.