A Letter of Map Amendment, called a LOMA, is a FEMA letter that says a structure or parcel of land on naturally high ground would not be flooded by the base flood, and for a LOMA FEMA charges no review and processing fee. FEMA issues the letter. If you are looking at homes for sale in Winnebago County, this is the federal process for asking FEMA to take a single house or lot out of a mapped flood zone.
The base flood is the flood with a one percent chance of happening in any given year. Land the flood map places inside that area is called a Special Flood Hazard Area. It is a letter about one property that amends the effective map. This guide walks through what a LOMA is, how it differs from its cousin the LOMR-F, what an owner has to supply, which form fits, what FEMA says about cost and timing, and what a letter does not change. Everything here comes from FEMA, floodsmart.gov and two local pages. It is information about how a federal rule works, not legal, insurance or engineering advice.
FEMA groups these requests under the name Letter of Map Change. The agency describes a Letter of Map Change as a request for a formal determination on whether a property is in a Special Flood Hazard Area. That is the area with a one percent or greater chance of flooding in any given year. Two of the letters matter most to a homeowner or a buyer, and the difference between them is simple.
A LOMA is for ground that was never low. FEMA's page describes it as a letter saying an existing structure or parcel sitting on naturally high ground, with no fill, would not be flooded by the base flood. FEMA's glossary puts it this way: "an official amendment, by letter, to an effective National Flood Insurance Program (NFIP) map." The glossary adds that it is typically granted when a property was wrongly placed in a flood zone even though it sits on high ground.
A Letter of Map Revision Based on Fill, or LOMR-F, is for ground that someone raised. FEMA describes it as a letter saying an existing structure or parcel that was raised with earthen fill would not be flooded by the base flood. The two letters sound alike and they reach the same kind of result, but the rules around them are not the same. A LOMR-F asks FEMA to agree that land which was once low is now high enough, and it brings the local government into the decision.
There are also revisions to the map itself, which FEMA calls a Letter of Map Revision and a Conditional Letter of Map Revision. Those are filed on a different form, the MT-2, and they cover revisions to flood studies and maps instead of amendments for one lot. The rest of this guide covers the first two.
One more point of vocabulary helps before the paperwork. FEMA calls the flood with a one percent annual chance the base flood, and it also calls it the 100-year flood. Zone X shaded sits between the base flood and the 0.2 percent annual chance flood, also called the 500-year flood. Zone X unshaded is the area of minimal flood hazard outside the Special Flood Hazard Area. The high-risk labels are Zones A, AE, AH, AO, AR and A99.
The test in each case is about elevation. For a structure under a LOMA, the lowest adjacent grade must be at or above the base flood elevation. For a lot under a LOMA, the lowest point on the lot must be at or above that elevation. The LOMR-F test for a structure is also lowest adjacent grade at or above the base flood elevation, and in addition the participating community has to determine that the land and structures are "reasonably safe from flooding." For a lot under a LOMR-F, both the lowest point on the lot and the lowest floor of the structure must be at or above the one percent annual chance flood elevation.
Lowest adjacent grade needs its own plain explanation, because it decides most requests. For a structure, FEMA says to indicate the lowest ground touching the structure, and that includes any attached deck or garage. For a property, you indicate the lowest ground elevation on the property. FEMA asks for elevations to the nearest tenth of a foot or meter, tied to the same datum the community's official map uses. A datum is the reference point for measuring height.
Because the numbers must be certified, the supporting paperwork usually involves a professional. FEMA says an applicant generally needs an Elevation Certificate prepared by a Licensed Land Surveyor or Registered Professional Engineer. The requester supplies everything FEMA needs, including elevation information certified by a surveyor or engineer. Floodsmart.gov describes an elevation certificate as a document that shows how high a building sits compared with how high local floodwaters are expected to rise. It records the First Floor Height, which is the height of the lowest floor above the ground, and basements are measured separately.
Here is a point that saves money. Floodsmart.gov says your local floodplain manager may already have an elevation certificate on file, usually through a city or county building, permitting, engineering or land use department. If one does not exist, the same page says to hire a land surveyor, engineer or architect to complete it. So the first call is to the office that holds records for the address, before anyone books a surveyor. The City of Rockford's stormwater page lists 779-348-7175 and stormwater@rockfordil.gov for questions.
Then comes the form. FEMA assigns the paperwork this way. The MT-EZ is for a LOMA request covering a single residential lot or structure, and FEMA calls it the condensed version of the MT-1. It applies only if the structure or land is on natural grade, meaning it has not been raised by fill, and the parcel must be described by metes and bounds certified by a Registered Professional Engineer or Licensed Land Surveyor. The MT-1 package, and the Online LOMC application, are for a LOMA covering multiple residential lots or structures and for every LOMR-F request. The MT-1 also covers the conditional versions of those letters. FEMA adds a note for a property inadvertently included in a V zone or a regulatory floodway. It may use these forms too, but to be removed from a V zone it must not be seaward of the landward toe of the primary frontal dune.
In short, a homeowner with a single house on a natural rise uses the MT-EZ. Anyone asking about fill, or about several lots, uses the MT-1 package. The MT-2 is for the other kind of change, a revision to the flood study or map.
FEMA's Change Your Flood Zone page describes three ways to file. Homeowners, renters, community officials and other individuals can use Online LOMC, or they can mail the paper forms. Land surveyors, professional engineers and other FEMA-permitted certified professionals can use eLOMA, and FEMA says a registered user can get a determination within minutes of submitting the required information. The mailing address for paper requests is the LOMC Clearinghouse, 3601 Eisenhower Avenue, Suite 500, Alexandria, VA 22304-6426. The Online LOMC help contents list an Elevation Form, a Community Acknowledgment Form and Endangered Species Act compliance among the items an application can involve, though the answers behind those headings are not shown on that page.
The community piece deserves a sentence of its own. On a LOMR-F, the community has to determine that the land is reasonably safe from flooding. FEMA also says the community must make sure permits are obtained under Section 60.3(a)(2) of its regulations, which is the Endangered Species Act compliance item. The town or county floodplain office is part of the sequence. A LOMA, by contrast, comes with a record-keeping duty after it is issued. FEMA's glossary says it becomes a public record the community must keep, noted on the community's master flood map and filed by panel number in an accessible location.
FEMA states the cost split plainly. A LOMA has no review and processing fee. A LOMR-F carries a fee, and the page that lists the requirements gives no amount. The paper application page says a review fee and a processing fee must come with the complete package for the MT-1 and MT-2 request types it lists, and it does not name a figure either. Paper requests of those types must also include the FEMA Payment Information Form. Online LOMC lets an applicant pay any associated fees. So the honest answer to "what will it cost" has two parts. The FEMA charge for a LOMA is nothing. Everything else, such as the surveyor or engineer and the elevation certificate, is outside what these FEMA pages list, so ask for a quote before you commit.
Timing has two clocks. FEMA says it notifies the applicant whether the submittal is complete within 30 days. It says the determination is normally issued within 60 days of receiving all required data. FEMA ties the 60 days to receiving all required data. FEMA does not publish a processing time for a LOMR-F on the page read for this guide. If you applied online, FEMA says you can check your application status by logging into your account. For a paper application, the status explanations are on the paper application forms page. For a question about a specific map change, FEMA's page points to a map specialist at the FEMA Mapping and Insurance eXchange, and floodsmart.gov lists that line as 877-336-2627.
Now the part buyers most often misread. A LOMA or a LOMR-F eliminates the federal flood insurance purchase requirement for federal or federally backed financing. That is a narrow statement. FEMA also says the mortgage lender can still require flood insurance as a condition of financing, regardless of location. Floodsmart.gov says the same in different words: owners in a Special Flood Hazard Area with a government-backed mortgage must carry flood insurance, and some lenders require it outside high-risk areas. So a letter changes the federal rule. It does not bind the lender to drop its own requirement, and a buyer should ask the lender, in writing, what it will require after the letter.
Think through a plain example. A buyer under contract on a house in Winnebago County finds, in the lender's flood determination, that the lot sits inside a mapped high-risk area. The buyer asks the seller for an elevation certificate. If the lowest ground touching the house is at or above the base flood elevation, and the house is on natural grade, the MT-EZ may fit. If someone brought in fill years ago to raise the pad, the request moves to the MT-1 package and the LOMR-F test, which also needs the community's determination. The example is an illustration of how the process fits together and is not a prediction for any address.
Insurance outside the line is the other half of the picture. FEMA's own page says buying a policy is still wise outside the Special Flood Hazard Area. It says more than 25 percent of flood claims come from properties outside that area. Floodsmart.gov gives a looser version, roughly 1 in 3 claims from low and moderate risk zones, and the two pages give different figures, so quote the one from the page you are reading. FEMA also says a LOMA or LOMR-F does not make a property safe from all flooding, because events greater than the one percent annual chance event can occur. And it says premiums for structures outside the Special Flood Hazard Area are lower than inside it. That last sentence is a relative statement, not a quote, so ask an insurance agent for an actual figure for the address.
A few practical notes on policies. Floodsmart.gov says coverage goes into effect 30 days after the date of purchase, with no wait if you buy while making, increasing, extending or renewing a mortgage. Policies last one year, and floodsmart.gov says every provider offers the same rates.
Where do you check the map first? FEMA's Map Service Center and the National Flood Hazard Layer both let you search by address. The viewer can print a full flood map or a smaller printable one called a FIRMette. The City of Rockford's page says its latest flood maps are effective February 17, 2016, and links to the Map Service Center and Winnebago County GIS for checking a property. That is a Rockford page, so check the effective date for your own community. The county's surface water ordinance applies to the unincorporated areas of Winnebago County. The county says adopting and enforcing it allowed the Flood Insurance Administration to make flood insurance available to residents and businesses there.
One last distinction keeps people from confusing two processes. When FEMA updates the maps for a whole community, there is a 90-day appeal and comment period and a Letter of Final Determination, and the new map takes effect six months later. FEMA's guide says a property owner who submits more precise mapping and survey data may allow FEMA to move a building from a Special Flood Hazard Area to Zone X. That is a community-wide cycle on FEMA's schedule. A LOMA is the property-by-property route instead.
A LOMA is worth looking into when a house or lot sits on natural high ground and the flood map still shows it inside a Special Flood Hazard Area. The FEMA fee for a LOMA is nothing, the determination is normally issued within 60 days of a complete package, and the MT-EZ is the short form for one residential lot or structure. The cost these FEMA pages leave out is the certified elevation work, so start by asking the local floodplain office whether a certificate is already on file for the address.
Be careful about what you promise yourself. A LOMR-F carries a FEMA fee and needs the community's sign-off. A letter ends the federal purchase requirement and nothing more. Your lender can still require a policy, and flooding above the one percent event can still happen. If you are weighing a purchase, compare the lender's written position and an insurance agent's quote before you count on any letter. For more on mapped areas near you, our guide to Rockford Flood Zones and Flood Insurance Guide covers the city, our guide to Winnebago County Floodplain Permits: Unincorporated Land covers the county side, and our guide to Title Search vs Title Insurance vs Survey in Illinois explains what a survey does. Gambino Realtors has served this area since 1923, and you can start your search among the homes for sale in Winnebago County. The full list of guides is in the Illinois Real Estate Guide: Every Gambino Realtors Article.
The questions below come up whenever a flood zone shows on a lender's paperwork. Here are plain answers from the FEMA pages.
A LOMA is for a structure or parcel on naturally high ground with no fill. A LOMR-F is for a structure or parcel that was raised with earthen fill. FEMA charges no review and processing fee for a LOMA and does charge a fee for a LOMR-F, though its requirements page lists no amount. A LOMR-F also needs the participating community to determine that the land and structures are reasonably safe from flooding. Both ask FEMA for a determination on whether the property is in a Special Flood Hazard Area.
FEMA describes the MT-EZ as the condensed version of the MT-1, used for a LOMA request covering a single residential lot or structure. It applies only when the structure or land is on natural grade, meaning not raised by fill, and the parcel is described by metes and bounds certified by a Registered Professional Engineer or Licensed Land Surveyor. Requests for multiple lots or structures, and all LOMR-F requests, go through the MT-1 package or the Online LOMC application.
FEMA says it notifies the applicant whether the submittal is complete within 30 days. It says the determination is normally issued within 60 days of receiving all required data. If you applied online, FEMA says you can check your application status by logging into your account. For a question about a specific map change, FEMA points to a map specialist at the FEMA Mapping and Insurance eXchange, listed on floodsmart.gov as 877-336-2627.
FEMA says an applicant generally needs an Elevation Certificate prepared by a Licensed Land Surveyor or Registered Professional Engineer. Floodsmart.gov says your local floodplain manager may already have one on file, usually through a city or county building, permitting, engineering or land use department. If none exists, you would hire a land surveyor, engineer or architect to complete one. Ask the office that holds records for the address first.
Yes. FEMA says a LOMA or LOMR-F eliminates the federal flood insurance purchase requirement for federal or federally backed financing. It also says the mortgage lender can still require flood insurance as a condition of financing, regardless of location. Floodsmart.gov says the same, that some lenders require it outside high-risk areas. Ask your lender in writing what it will require after a letter is issued.
No. FEMA says a LOMA or LOMR-F does not make a property safe from all flooding, because events greater than the one percent annual chance event can occur. It also says more than 25 percent of flood claims come from properties outside the Special Flood Hazard Area, and that buying a policy is still wise there. Premiums for structures outside the Special Flood Hazard Area are lower than inside it, so ask an insurance agent about the address.